December 5, 2004: Panarama
Building the 14th cable bundle (west, channel side)
, disassembly of the west approach crane, preparing to build the 13th cable
bundle (east, approach side) and removing the hurricane cables (compare the
east (right) with the west (left).
Main Span
West Pylon: No Hurricane cables
|
East Pylon: Hurricane cables still visible
|
|
|
December 5, 2004
Building the east approach 13th cable bundle -
cable rig is now in place and disassembly of the west approach crane.
The counterweights have been removed from the west platform now that it
is attached to the west approach. You can see the counterweights on the
east platform (channel side, left) which will be removed once the east
platform is attached to the east approach. In addition, the hurricane
cables have been removed from the west deck.
West Approach
Note the hurricane cables have been removed
East Approach
Note counterweights on the channel side
West Approach: It appears that the crane has been disassembled (tear down time?)
|
East Approach: The cable building rig has been moved into position adjacent
to the 13th anchor (on the edge girder erected last week)
|
|
|
This work is licensed under a Creative Commons License.
Attribution: C. Frank Starmer from http://ravenelbridge.net