|
T.S. Eliot (East Coker from the Four Quartets) put it this way:
Old men ought to be explorers
Here and there does not matter
We must be still and still moving
Into another intensity
For a further union, a deeper communion
The new Cooper River Bridge (Arthur Ravenel Bridge) has a 1546
foot main span, the longest cable-stayed span in North America.
Each side span is 650 fee and the end psans are 225 feet resulting
in a main span unit length of 3,296 feet. Each main span tower
is 570 feet tall and supported by 11 drilled shafts. Each
shaft is 10 feet in diameter and extends 230 feet down. This
supporting structure is protected from ship impacts by rock
islands surrounding the tower foundations.
The first foundation drilling started in April 2002 and construction was completed by July 2005, one year ahead of schedule. The tower, cable and main span construction was staggered so that any problems encountered with the west segment could be resolved and incorporated with contruction of the east segment. Consequently when viewing the photos, the east tower height is slightly less than the west tower hight until completed. The project was a design-build project. Design-Build is a construction project delivery process used to reduce construction time by overlapping some of the design with various phases of the construction. The result was completion one year ahead of schedule. In August 2003, I began to keep this record for my grandchildren. As the weeks passed, I became more and more fascinated by the processes of bridge construction (being an engineer) and so began to pursue more detail. These photos show the development of the west (taller) and east towers (pylons) as seen from the South Carolina Aquarium. There are 64 cable stays attached to each tower, 32 supporting the east span and 32 supporting the west span. Thus there are a total of 128 cable bundles. Each cable bundle is comprised of 31 to 90 steel strands depending on the length and load of the roadbed, with bundles of 31 strand cables closest to the tower and bundles of 90 strands farthest away. The edge girders with the steel anchors for the cable stays have a distinct fin and are called shark fin girders. You can see them projecting upward from the edges of the roadbed. By May 2004, to my photos from the SC Aquarium, I added photos taken early each Saturday or Sunday morning from my bicycle as I rode across the Pearman bridge. Here I would watch the building processes: construction of the mainspan (roadbed) platforms, cantilevering out from the pylons and held in place by the cable stays. There are 64 cables were attached to each tower, 32 supporting the east span and 32 supporting the west span for a total of 128 cables. Each cable was comprised of 31 to 90 strands depending on length and load with the 31 stand cables adjacent to the tower and the 90 strand cables linking anchors along the main and back span edge girders. Because the edge girders and the steel anchors appeared as a shark fin, the edge girders were called shark fin girders. Fog was the least of the weather challenges for the design of the bridge. The bridge was designed to withstand wind speeds up to 190 mph and during construction, the main span was anchored to the rock islands with temporary hurricane cables. With the hydraulic jacks correcting the horizontal alignment pins are inserted in the splice plate and through the girder in order to hold the splice plate in position while the other holes are bolted. One of the hallmarks of this project from my perspective was the close personal relationship between all workers on the bridge. Literally, lives depended on close, accurate and timely communication. The management of this project was excellent. Everyone worked as part of a team. I often noticed this when looking over their shoulders to take these pictures. |